NSC PREPARATORY WORKS. BERM PIONEER WALL REMOVAL

Description:

NSC Preparatory Works. Berm Pioneer Wall    Removal. SSE ChNPP

Kinds of works:

  • Water suppression of dust held in the general area – 103250 м2

  • berm power plate cut – 1957 м2

  • berm destruction of structures made by breakers; loading – 2871 м3

  •  screening conducted in the areas of production site – 61м2

  • developed man-made fill – 14574 м3

  • fitting is cut – 86,27 т

  • dismantled structures of entrance ramp – 430 м3

  • removal of access road and rotating platform – 35 м3

  • berm power plate fragments loading – 1288,1 м3