NSC Preparatory Works. Berm Pioneer Wall Removal. SSE ChNPP
Water suppression of dust held in the general area – 103250 м2
berm power plate cut – 1957 м2
berm destruction of structures made by breakers; loading – 2871 м3
screening conducted in the areas of production site – 61м2
developed man-made fill – 14574 м3
fitting is cut – 86,27 т
dismantled structures of entrance ramp – 430 м3
removal of access road and rotating platform – 35 м3
berm power plate fragments loading – 1288,1 м3